Palmetto Site Prep, LLC

1737 Joe S. Jeffords Hwy

PO Box 1323 

Orangeburg, SC 29115

 

Phone: (803) 536-3143

Fax: (803) 585-0029

 

Completed Projects

   

North Shore

      Santee, SC   

 

North Shore is a premier condominium development on the shores of Lake Marion in North Santee, S.C. Palmetto Site Prep has been involved in this project from design through construction. We began this project with soft clearing and under brushing to facilitate pre-construction sales activities. This activity began in August of 2006. Actual constructionbegan in December of 2006. This project has incorporated an environmentally friendly design in order to maintain the natural beauty of the property. This includes: green areas and nature trails that Palmetto Site Prep has helped develop throughout the property.

          

               

 

 

  Ballards Pointe

  Santee, SC

Ballards Pointe is a growing condominium development in Santee. Currently in the third phase of development, Ballards was started in the spring of 2004.Palmetto Site Prep has been involved in all aspects of site development on these projects. This included underground water and sewer construction, mass grading, and specialty storm structures. Through close work with the developer, Palmetto Site Prep has been able to deliver on or ahead of schedule for each of these projects.    

 

Willington Lakes Apartments 

Orangeburg, SC

Willington Lakes is an upscale apartment community in Orangeburg. Palmetto  Site Prep handled clearing, grading, water  and sewer installation, and asphalt paving on this  project.

 

 

 

The Okonite Company 

     Orangeburg, SC                                                      

           

 Palmetto Site Prep has been involved in three major expansions with The Okonite Company over a two year period. The first expansion began in December of 2005. We came into the project behind. An out of state contractor left the entire project in very bad shape and behind schedule. Through the hard work and skills of our grading crew, we were able to pull the project back on schedule. The expansion included a 60,000 sq. ft. expansion on their CV Building with related site work. This project was completed in August of 2006.

 

In February of 2007, we began construction for the new Rewind Building. This project included a 48,000 sq. ft. building and 100,000 sq. ft. of exterior wire, reel storage pads, and trailer staging areas. This project was completed on schedule in September of 2007.

 

In April of 2007, we began another expansion of the CV Building. This job included 37,000 sq. ft. building expansion and a 4,000 sq. yd. asphalt parking lot addition with related storm and roof drain work. We also handled the relocation of underground fire lines that serviced this section of the building. This project was completed on schedule in December of 2007.  

                                                                                                                                                                                                                                                    

Throughout these projects, we have developed an excellent relationship with both, The Okonite Company and Denham-Blythe, the General Contractor, on all of these projects.

 

 

 

 

 

  

 

 

 

 

  

 

 

 

Monteferro          

  Orangeburg, SC

 

   Monteferro is an industry leader in the field of Elevator guide rails and hoist  way systems. Our activities on this project included 20,000 cubic yd. of cut and fill, canal relocation, 45,000 sq. ft. building pad, and 68,000 sq. ft. of employee and truck parking.  This project was started in October of 2007. Despite heavy weather delays we managed to keep this project on schedule. Project was completed in May of 2008.   

                                                                                                                                                                                                                                                                                                                   

 

Orangeburg County/ City Industrial Park Phase II

Orangeburg, SC

 

This Industrial Park expansion included approximately 5 acres of clearing and

 grubbing, 5,500 LF of various sized RCP storm drain with related boxes, 5,200 LF of 10’DI water main, 4,300 LF of 10’ gravity sewer,  12,000 LF of curb and gutter, and 19,000 sq. yd. of asphalt  paving. This project’s schedule was fast tracked by the announcement of new industry moving into the undeveloped section of the park. 

Palmetto Site Prep has persevered though numerous weather delays on this project and provided the first 1,500 LF of road to allow the opening of the new industry on schedule. Project completion is set for early summer of 2008.